We're happy to announce that after roughly a month of allowing current customers to get redeployed, we have now starting accepting miners from new customers.
Please send us an email: POSTED BY Joshua Holmes IN GENERAL ON
Filter by: dataCenter
We're happy to announce that after roughly a month of allowing current customers to get redeployed, we have now starting accepting miners from new customers.
Please send us an email: POSTED BY Joshua Holmes IN GENERAL ON
It's been a long road (vastly longer than expected), however, yesterday (March 24th) we received the go-ahead from our ...
POSTED BY Joshua Holmes IN GENERAL ONHello LightSpeeders,
We're coming down the wire on the expansion facility (pun intended). This expansion has ran into several supply chain issues, vastly more than we could ...
POSTED BY Joshua Holmes IN GENERAL ONAfter many years of searching, planning and writing down all the things we would do different on a new facility, LightSpeed is ready to start the tedious process of migrating its existing 4 year ol...
POSTED BY Joshua Holmes IN GENERAL ONEver want to see what it looks like in a data center specifically designed for cryptocurrency miners? Here's your chance!
The mining industry as a whole tends to operate different than...
POSTED BY Joshua Holmes IN GENERAL ONIt was only a matter of time before other ASIC miner manufacturers come out with machines to compete with the Bitmain Joshua IN GENERAL ON
With the growing number of clients wanting to pay using cryptocurrencies, LightSpeed Hosting has teamed up with CoinPayments to offer online Cryptocurrency payments for all services.
<...
POSTED BY Joshua IN GENERAL ONSecurity vulnerabilities continue to make headlines, but these two are huge. Here's what you need to know.
Staging & Development Moved!
After 11 months, thousands of man hours and plenty of cash, LightSpeed Hosting, is just a few weeks away from opening. The last week o...
POSTED BY Joshua IN GENERAL ONThe finish work has begun. In the server and electrical/UPS rooms we're going to be using an anti-static epoxy on the floor rather than raised floor. This will allow us to cut costs, ru...
POSTED BY Joshua Holmes IN GENERAL ONThe outdoor infrastructure is getting underway. Outside we have a new transformer pad, generator and ATS (Automatic Transfer Switch) pad, along with new natural gas run from the main just for...
POSTED BY Joshua Holmes IN GENERAL ONWell folks, we're getting close now to really entering a phase where we can starting running high voltage, UPS, network conduit etc. New doors are being hung, stained etc.
Along with f...
POSTED BY Joshua Holmes IN GENERAL ONIt's official, we're done with the initial architecture phase and building of walls and mezzanine structure has begun. The smaller room on the right will be our electrical and UPS room, and t...
POSTED BY Joshua Holmes IN GENERAL ONJanuary of this year, we decided on a bare warehouse as our starting point for our new data center. We had a lot of important criterial. Among the most important criteria we were lookin...
POSTED BY Joshua Holmes IN GENERAL ON